Following a flood event ORC\u2019s Flood Protection, Drainage and\nRiver Management function is required to identify and prioritise damage and\ncommunicate a repair programme with affected communities within three months of\nthe event.<\/div>

In July and August 2022 there were four successive rainfall\nevents that impacted on Otago\u2019s rivers and flood protection and drainage\nschemes:<\/div>
\n\n
    \n
  • 12-14 July 2022 (Dunedin and Coastal Otago)<\/span><\/li>\n
  • 17-20 July 2022 (Central Otago and Queenstown Lakes)<\/span><\/li>\n
  • 25-29 July 2022 (Dunedin and Coastal Otago)<\/span><\/li>\n
  • 5-8 August 2022 (Headwaters of the Queenstown Lakes,\n impacting the Lower Clutha Flood Protection and Drainage Scheme)<\/span><\/li>\n<\/ul>\n\n

    Damage assessments are undertaken once water levels subside,\nand the successive nature of this event sequence meant that a full damage\nassessment could not be completed until a reduction in river flows after the\nlast rainfall event of the sequence (i.e. after 8 August).<\/p>
    <\/div>", "mapName": "FloodRecoveryWorks (Public)", "description": "Public layer of Engineering Works Program showing the status of incidents post flood event.Following a flood event ORC\u2019s Flood Protection, Drainage and\nRiver Management function is required to identify and prioritise damage and\ncommunicate a repair programme with affected communities within three months of\nthe event.In July and August 2022 there were four successive rainfall\nevents that impacted on Otago\u2019s rivers and flood protection and drainage\nschemes:\n\n\n 12-14 July 2022 (Dunedin and Coastal Otago)\n 17-20 July 2022 (Central Otago and Queenstown Lakes)\n 25-29 July 2022 (Dunedin and Coastal Otago)\n 5-8 August 2022 (Headwaters of the Queenstown Lakes,\n impacting the Lower Clutha Flood Protection and Drainage Scheme)\n\n\nDamage assessments are undertaken once water levels subside,\nand the successive nature of this event sequence meant that a full damage\nassessment could not be completed until a reduction in river flows after the\nlast rainfall event of the sequence (i.e. after 8 August).", "copyrightText": "Otago Regional Council", "supportsDynamicLayers": true, "layers": [ { "id": 0, "name": "Flood Recovery Works", "parentLayerId": -1, "defaultVisibility": true, "subLayerIds": null, "minScale": 5000000, "maxScale": 32000, "type": "Feature Layer", "geometryType": "esriGeometryPoint", "supportsDynamicLegends": true } ], "tables": [], "spatialReference": { "wkid": 2193, "latestWkid": 2193, "xyTolerance": 0.001, "zTolerance": 0.001, "mTolerance": 0.001, "falseX": -4020900, "falseY": 1900, "xyUnits": 10000, "falseZ": -100000, "zUnits": 10000, "falseM": -100000, "mUnits": 10000 }, "singleFusedMapCache": false, "initialExtent": { "xmin": 1045198.94178163, "ymin": 4764696.307821829, "xmax": 1613483.0584656063, "ymax": 5148628.2794697825, "spatialReference": { "wkid": 2193, "latestWkid": 2193, "xyTolerance": 0.001, "zTolerance": 0.001, "mTolerance": 0.001, "falseX": -4020900, "falseY": 1900, "xyUnits": 10000, "falseZ": -100000, "zUnits": 10000, "falseM": -100000, "mUnits": 10000 } }, "fullExtent": { "xmin": 1232784.3128000004, "ymin": 4860958.4408, "xmax": 1436666.7183999997, "ymax": 5045417.7579, "spatialReference": { "wkid": 2193, "latestWkid": 2193, "xyTolerance": 0.001, "zTolerance": 0.001, "mTolerance": 0.001, "falseX": -4020900, "falseY": 1900, "xyUnits": 10000, "falseZ": -100000, "zUnits": 10000, "falseM": -100000, "mUnits": 10000 } }, "datesInUnknownTimezone": false, "minScale": 5000000, "maxScale": 32000, "units": "esriMeters", "supportedImageFormatTypes": "PNG32,PNG24,PNG,JPG,DIB,TIFF,EMF,PS,PDF,GIF,SVG,SVGZ,BMP", "documentInfo": { "Title": "Flood Recovery Works", "Author": "", "Comments": "Engineering works program showing the status of incidents post flood event.", "Subject": "Flood Recovery Works List points", "Category": "", "AntialiasingMode": "Fast", "TextAntialiasingMode": "Force", "Version": "2.9.0", "Keywords": "Engineering,Flood,Recovery,River,Scheme,Otago" }, "supportsQueryDomains": true, "capabilities": "Map,Query,Data", "supportedQueryFormats": "JSON, geoJSON, PBF", "exportTilesAllowed": false, "referenceScale": 0.0, "datumTransformations": [ { "geoTransforms": [ { "wkid": 1565, "latestWkid": 1565, "transformForward": false, "name": "NZGD_2000_To_WGS_1984_1" } ] }, { "geoTransforms": [ { "wkid": 1565, "latestWkid": 1565, "transformForward": true, "name": "NZGD_2000_To_WGS_1984_1" } ] } ], "supportsDatumTransformation": true, "floorAwareMapProperties": { "defaultFloorFilterSettings": {"isEnabled": false} }, "archivingInfo": {"supportsHistoricMoment": false}, "supportsClipping": true, "supportsSpatialFilter": true, "supportsTimeRelation": true, "supportsQueryDataElements": true, "maxRecordCount": 2000, "maxImageHeight": 4096, "maxImageWidth": 4096, "supportedExtensions": "", "resampling": false, "serviceItemId": "2d8eeb36b46c4e77bbbd7ad8b2047ef6" }